Turnkey campus-wide ELV and ICT infrastructure across the 55-acre AL-Karim University campus in Katihar, Bihar, encompassing approximately 450–500 km of structured cabling, 35 km fibre infrastructure, 1,800+ data points, 1,000+ wireless access points, 500+ IP telephony endpoints, 8 flap barriers, data centre setup, AV conferencing, and environmental detection systems.

+
PROJECT PHOTOGRAPHY ARCHIVEFIELD MEDIA SUBJECT TO CLIENT CLEARANCE
SPECIFICATION: DOCUMENTEDRECORD REF: HNT-PRJ-001

02 • PROJECT REGISTER • TECHNICAL SPECIFICATION

OFFICIAL RECORD
REGISTER FIELDVERIFIED RECORD VALUE
PROJECT IDHNT-PRJ-001
CLIENT / CLEARANCEAL-Karim University
LOCATIONKatihar, Bihar
SCALE & COMPLEXITYApproximately 450–500 km of structured cabling and 35 km of fibre infrastructure formed the connectivity backbone, supporting 1,800+ data points, 1,000+ wireless access points and 500+ IP telephony endpoints across 50–55 campus buildings on a 55-acre university site.
FACILITY TYPE55-Acre University Campus (~50–55 Buildings)
INDUSTRY / SECTOREducation & Institutional Campuses
PRIMARY DISCIPLINENetwork & Data
PROJECT CATEGORIESData Centres & Hub Rooms, Security & Access, AV / Video Walls / Conferencing, Mission-Critical Infrastructure
PROJECT / CONTRACT MODELCampus Infrastructure Deployment
CONTRACT TYPETurnkey ICT & ELV Systems Integration
PROJECT STATUSCommissioned & Handed Over
VERIFICATION STATUSPublic Engineering Case

03 • PROJECT BRIEF • FACILITY ENVIRONMENT & REQUIREMENTS

Operational Requirement & Context

Deployment across a 55-acre university campus comprising approximately 50–55 buildings, requiring campus-wide structured cabling and fibre infrastructure, networking, wireless connectivity, IP telephony, central data centre setup, pedestrian flap barrier access, AV conferencing, and environmental detection systems (VESDA, water leak detection, rodent detection).

PUBLICATION-SAFE DESCRIPTION (NDA CLEARED)

HORNET INFOTECH delivered integrated ELV and ICT infrastructure across the 55-acre AL-Karim University campus in Katihar, Bihar. The deployment combined extensive structured cabling and fibre infrastructure with networking, wireless connectivity, IP telephony, data-centre infrastructure, access control, AV conferencing and critical environmental detection systems.

04 • HORNET SCOPE REGISTER

DELIVERY CATEGORIES
SCOPE 03

Hardware & OEM Procurement

  • •Structured cabling and fibre infrastructure distribution components
  • •Campus networking equipment, 1,000+ wireless access points, and 500+ IP telephony endpoints
  • •8 pedestrian flap barrier turnstile units and access control hardware
  • •Data centre environmental detection equipment: VESDA, water leak detection (WLD), and rodent detection hardware
  • •Windows and other software licences
SCOPE 04

On-Site Installation & Cabling

  • •Installation of approximately 450–500 km structured cabling
  • •Deployment of 35 km fibre infrastructure across campus buildings
  • •Installation of 1,800+ data points and 1,000+ wireless access points
  • •Installation of 500+ IP telephony endpoints across campus facilities
  • •Installation of 8 pedestrian flap barriers
  • •Data centre setup with water leak detection, VESDA, and rodent detection
SCOPE 05

Multi-Vendor Systems Integration

  • •Campus networking and wireless connectivity integration
  • •IP telephony system integration across university facilities
  • •Access control integration on 8 pedestrian flap barriers
  • •Data centre setup integration including VESDA, water leak detection, and rodent detection
  • •AV conferencing solution integration

05 • DELIVERED SYSTEMS & SCHEMATIC ANCHORS

10 SUBSYSTEMS
SUBSYSTEM S-01

Structured Cabling Infrastructure

Approximately 450–500 km of structured cabling supporting 1,800+ data points across ~50–55 campus buildings.

CANONICAL SOLUTION SCHEMATIC
SUBSYSTEM S-02

Campus Fibre Infrastructure Backbone

35 km of fibre infrastructure connecting facilities across the 55-acre university campus.

CANONICAL SOLUTION SCHEMATIC
SUBSYSTEM S-03

Enterprise Networking & Wireless Infrastructure

Campus networking distribution powering 1,000+ wireless access points for campus-wide coverage.

CANONICAL SOLUTION SCHEMATIC
SUBSYSTEM S-04

Enterprise IP Telephony

Voice communication deployment servicing 500+ IP telephony endpoints across university facilities.

CANONICAL SOLUTION SCHEMATIC
SUBSYSTEM S-05

Data Centre Setup

Central campus data centre setup housing core computing, storage, and networking distribution infrastructure.

CANONICAL SOLUTION SCHEMATIC
SUBSYSTEM S-06

Pedestrian Flap Barriers & Access Control

8 automated flap barrier turnstile units for controlled pedestrian access.

CANONICAL SOLUTION SCHEMATIC
SUBSYSTEM S-07

AV & Video Conferencing

Audio-visual conferencing solution for institutional collaboration.

CANONICAL SOLUTION SCHEMATIC
SUBSYSTEM S-08

VESDA Aspirating Smoke Detection

VESDA aspirating air-sampling smoke detection for the central data centre setup.

CANONICAL SOLUTION SCHEMATIC
SUBSYSTEM S-09

Water Leak Detection (WLD)

Water leak detection system for critical data centre areas.

CANONICAL SOLUTION SCHEMATIC
SUBSYSTEM S-010

Rodent Detection System

Rodent detection system for cable pathways and data centre areas.

CANONICAL SOLUTION SCHEMATIC

07 • TECHNICAL DRAWINGS • ENGINEERING EVIDENCE

CAD / SCHEMATICS / HIGHLIGHTS
ENGINEERING HIGHLIGHTS & FIELD METRICS
  • •Scale: Approximately 450–500 km of structured cabling deployed across ~50–55 campus buildings
  • •Fibre Infrastructure: 35 km of fibre infrastructure connecting facilities across the 55-acre university campus
  • •Endpoint Scale: Deployment supporting 1,800+ data points, 1,000+ wireless access points, and 500+ IP telephony endpoints
  • •Data Centre Environmental Protection: Central data centre setup incorporating VESDA, water leak detection, and rodent detection

09 • PROJECT OUTCOME & COMMISSIONING HANDOVER

Documented Handover Deliverables

Delivered, commissioned, and handed over as operational campus-wide ICT and ELV infrastructure for AL-Karim University.

12 • PROJECT INQUIRY

DISCUSS A SIMILAR ENGINEERING REQUIREMENT

Connect with HORNET INFOTECH systems engineers to review ELV, ICT, fire & life safety, and critical facility schematics tailored to your deployment specifications.

HORNET INFOTECH

J-50, Abul Fazal Enclave, Okhla, New Delhi-110025